Oct. 3, 2013 - the football team practices on the new fields
Sept. 6, 2013 - more landscaping is added around the fields….
and a new walkway leads down to the track and field area
Shot put area
Javelin area
Discus area
September 5, 2013 - the new fieldhouse is in use
August 27, 2013 - the new field house is ready for use
August 6, 2013 - exterior of the field house
August 6, 2013 - entryway to the field house
August 6, 2013 - the track
August 6, 2013 - equipment for the weight room is being installed
August 6, 2013 - Finishing touches are being put on the locker room
August 6, 2013 - The Training Room
June 2013
April 30, 2013 - view of the front
April 30, 2013 - view from the back
April 30, 2013 - turf is on the back field
April 2013 - the roof is put on
March 2013 - framing for the new field house is in place.
March 2013 - lighting for the new fields is installed.
Feb. 19, 2013 - workers smooth out the first 275 yards of concrete that were poured.
Feb. 14, 2013 - workers are getting the fieldhouse site ready for the foundation to be poured.
Dec. 4, 2012 - the parking lot for the fieldhouse is starting to take shape.
Oct. 30, 2012 - more progress on the roadbed
Oct. 2012 - The ground has been leveled and you can see where the road will go down to the new facilities
Sept. 2012 - Construction begins
(Photo credit: Lucas Adams)
(Photo credit: Lucas Adams)
Summer 2012 - before construction